A full kitchen renovation is a sequence of dependent steps, and most delays happen when that sequence is ignored. Here is how a well-run kitchen renovation in Johannesburg works from the first call to the final snag list, and how long each stage realistically takes.
1. Site Visit and Brief (Week 0)
A proper quote starts with a site visit, not a phone estimate. The contractor measures the room, checks where plumbing and electrical points sit, looks for damp or structural issues, and asks how you use the kitchen. Photos and a rough floor plan help, but they never replace a visit.
Come with a budget range, a style direction and a list of what frustrates you about the current kitchen. Those three things shape every later decision.
2. Design and Fixed Quote (Weeks 1–2)
You should receive a layout, material and finish selections, and an itemised fixed quote. The quote should list cabinetry, worktops, hardware, plumbing, electrical, tiling, painting, labour and project management separately, with a payment schedule tied to milestones.
- Check that appliances are either included or clearly excluded
- Check what happens if hidden problems are found behind walls
- Agree how variations are priced and approved in writing
3. Manufacture and Ordering (Weeks 2–5)
Once you sign off the design and pay the deposit, custom cabinetry is manufactured to measure while worktops, tiles, taps and appliances are ordered. Doing this before demolition keeps your kitchen out of action for as short a time as possible.
Stone worktops are templated after the cabinets are installed, which adds several days to the end of the schedule. Ask your contractor to build that into the timeline.
4. Strip-Out and First Fix (Week 5)
The old kitchen comes out, walls and floors are prepared, and plumbing and electrical first-fix work is completed. This is when hidden problems appear, such as old pipework, damp or non-compliant wiring. A contingency of 10–15% of the project value is sensible.
5. Installation (Weeks 5–7)
Cabinets are installed and levelled, worktops fitted, splashbacks and tiling completed, and plumbing and appliances connected. Most full kitchens take 2–4 weeks on site from strip-out to completion.
6. Finishing, Snagging and Handover
Painting, final adjustments, silicone, cleaning and a walk-through with you. Check every drawer, door and tap, and list any defects. A reputable contractor fixes them promptly and backs the work with a written warranty.
Where Renovations Go Wrong
The common causes of delay are changing the design after manufacture has begun, ordering worktops late, and discovering hidden defects without contingency. Plan decisions early and the process stays predictable.
Quick Answers
How long does a full kitchen renovation take in Johannesburg?
Typically 4–7 weeks from signed quote to handover, of which 2–4 weeks are on site. Design sign-off and manufacture account for the rest.
Can I live at home during a kitchen renovation?
Most clients do. Set up a temporary kitchen area and expect the main kitchen to be unusable for 2–4 weeks.